← Overrides that needed a leader

Override detail

OVR-202608-0100

TRAILER_RESEQUENCE · building BLD-4417 · 2026-08-01 · twilight shift · decided at L5

ESCALATE

What the shift leader did

Decision type
TRAILER_RESEQUENCE
From
SEQ-11
To
SEQ-3
Quantity moved
2
Reason code
EQUIPMENT_DOWN
Forecast confidence
74.6%
Downstream capacity
Minimum staffing intact
yes

What happened to the stores

Replenishment
no miss
On-time
95.0%

Constraint evaluation trace

The constraints in the order the policy evaluated them. Every constraint is evaluated even after one fails, so the whole picture is on the record; the first failure is the one that decides the verdict. Read from the signed payload.

#ConstraintRuleOutcomeObservedLimitReason code
1Minimum staffing intacthard-constraint-min-staffingpass11
2Forecast confidence at or above floorforecast-confidence-floorpass7,4607,000
3Decision type covered by a ruleuncovered-decision-typepass
4Downstream capacity at or above floortrailer-resequence-capacity-gatedfail8,500downstream_capacity_not_recorded
Verdict ESCALATE — decided by Downstream capacity at or above floor. Policy flow-center-v1.

Tamper-evidence

Record class
retrospective_evaluation_record
Proof id
proof-19668849-f15c-4d9f-b12e-d9f4b5dc6a54
Position in chain
3
Record hash
588b32360147a4b06a2f729b71b5e580307b6fb7bd4cb1fce29996238128e3bc
Previous record hash
fbf719ecb530b372d7f0bb1ba12df34d6fbd124ac50a973e496699800052188e
Input hash
bded7f65623ab1b7d344435efbc935dfbc9bf2f5e2be076393093f6dd87cefa5
Rules hash
02a2b9988da7bb1e33cb34a5abf231cc725021b33916c0e808fc234dcf27b64f
Signature
present (Ed25519)
Workflow
Flow-Center Operating Overrides Replay
Policy applied
Flow-Center Operating Policy · flow-center-v1
Sealed at
2026-09-16 03:57:35 UTC
Stored disposition
escalate

Verification is independent of the screen you are looking at: it recomputes the record from its own contents, checks the signature, and rehashes the payload against the input hash bound into the signed core.